An Indianapolis driveway permit is required when an abutting owner cuts into a curb, sidewalk, grassplot or the street pavement to build a driveway. The code names Construction and Business Services, a division of the city’s Department of Business and Neighborhood Services, as the permit office, and a separate section puts cuts in curbs and pavements under a public works permit. The city decides what applies. Carmel and Greenwood set their own rules.

What Sec. 645-421 Asks of a Property Owner

The rule sits in Indianapolis and Marion County’s Revised Code, quoted from the code on Municode as of Supplement 47 Update 2. The text of Sec. 645-421, “Permit required; enforcement,” is short.

Subsection (a) makes it unlawful for “any abutting owner” to alter, remove or cut a grassplot, a sidewalk, the street pavement or the curb next to it, or to excavate in a street, to build a driveway or roadway for vehicles to cross over. The condition is “without first obtaining a permit,” and the permit must come from the office named above.

Subsection (b) attaches “the enforcement procedures and penalties provided in section 103-3” and says “each day that an offense continues shall constitute a separate violation.” Ask the city what penalty applies.

For the pouring side, see Greater Indianapolis concrete driveways. We form and pour; who applies for a permit is a question to settle with the city.

The Public Works Permit for Curb and Pavement Cuts

Sec. 645-401, “Supervision of work,” covers “All work of making any cuts in pavements or curbs and excavations in streets or public ways.” Such work is to be done “under a permit from and subject to the supervision and approval of the director of public works,” with acceptance by the board of public works. The text of Sec. 645-401 is one sentence.

Sec. 645-423 sits in the driveway division and says work there is governed by “the same procedure and conditions” that apply to sidewalks and to excavations. A curb cut is a cut in a curb, so Sec. 645-401 may reach it, but neither section says how the two permits interact, so ask the city.

Division 3 covers excavations, with titles such as “Permit application” (Sec. 645-432), “Surety bond” (Sec. 645-438) and “Plans and specifications” (Sec. 645-439).

How the Finished Apron Must Work

Sec. 645-425, “Obstruction of sidewalk or drainage,” bars a driveway that causes “any hazard at any time” to people on the sidewalk crossing it. It also requires “free and unobstructed passage” and says the driveway cannot “interfere with the proper drainage and grade of the street.”

Sec. 645-426, “Maintenance of driveway,” puts upkeep on the person the permit was issued to, or that person’s successor in title, in a “well-paved and proper and reasonably safe state of repair.”

Sec. 645-424, “Allocation of costs,” puts driveway costs on the person owning or controlling the premises, “Unless otherwise ordered by the board of public works.”

Sec. 645-422, “Temporary driveways,” allows one during building or excavation work “in such manner and for such length of time as may be authorized by” the permit office.

When a Curb Cut Permit Ends

Sec. 645-427 is titled “Voidance of permit upon change of use or application for building permit for adjacent premises.” A curb cut permit “shall automatically terminate” upon a change in the business usage of the premises, “regardless of how slight or minor the change may be,” and when a building permit is applied for on adjacent premises that the permit gives access to. It does not say every building permit voids every driveway permit. The text of Sec. 645-427 has three subsections.

Sec. 645-428, “Restoration upon abandonment,” lets the permit office order abutting owners to restore a curb, sidewalk or pavement once a driveway is abandoned, and lets the city do the work and collect from the owner. Sec. 645-429, “Violations,” calls a driveway built, maintained or used contrary to the division, or not kept in good repair, “a violation of this Code.”

Questions to Settle Before the Quote

Put these to the city and the contractor quoting the job.

  • Does the work touch the curb, grassplot, sidewalk or street pavement?
  • Who applies for the permit, and in whose name?
  • Does a Sec. 645-401 permit also apply?
  • Is a building permit application planned for this lot or a neighboring one?
  • Are permit costs in the quote?
  • Will the apron keep the sidewalk passable and the street draining?

For how finishes are priced, see Indianapolis concrete driveway prices. For what each pour involves, see Indianapolis concrete services. When the plan is ready, ask for a free Indianapolis quote.

The right slab depends on the soil, the drainage, local permit rules and how the surface will be used. Requirements vary by site, scope and jurisdiction; the city or county permit office, and a site visit before the quote is final, determine what applies.

For hiring questions, read how to find a reliable concrete contractor.

Carmel and Greenwood sit outside the Revised Code; the Census place-by-county file for Indiana places them in Hamilton and Johnson counties, so ask that city’s office.

Frequently Asked Questions

Who needs a driveway permit under the Indianapolis code?

An abutting owner does, before altering, removing or cutting a grassplot, sidewalk, street pavement or curb for a driveway or roadway. The permit comes from Construction and Business Services, a division of the city’s Department of Business and Neighborhood Services.

Does Sec. 645-401 also apply to a driveway curb cut?

Sec. 645-401 covers cuts in pavements and curbs under a permit from the director of public works. Sec. 645-423 says driveway work follows the same procedure and conditions as sidewalks and excavations. How the two fit together is the city’s answer to give, so ask before the quote is final.

Can an Indianapolis curb cut permit end after it is issued?

Yes, in the situations Sec. 645-427 lists. It says a permit automatically terminates on a change in business usage of the premises, or when someone applies for a building permit on adjacent premises that the permit gives access to. Subsection (c) describes a petition to keep it. The city decides whether that reaches a given property.

Does the Indianapolis code apply in Carmel or Greenwood?

No. The Revised Code is Indianapolis and Marion County’s code. The Census file lists Carmel as an incorporated place in Hamilton County and Greenwood as one in Johnson County, so an owner there should check with that city’s own office.

Ready for a Free Quote?